Plastering
The whole kitchen diner and living room open plan is now plastered with the ceiling being plastered this morning.
The whole kitchen diner and living room open plan is now plastered with the ceiling being plastered this morning.
2 rsj’s are in and we have opened up this wall so the kitchen/diner/lounge will be a great size. 1 more rsj to go in the exterior wall to...
Shelving unit done Thursday this week to hold 5m long carpets. The structure could be holding up to about 2.5 tonnes at a time so we had...
Before and afters of a garage we painted earlier this week 👍
Our dining table is under construction today made from sycamore wood, 9ftx4ft
Stone on the back face has been laid and thermalite blocks on top of that are also layed, ready for cladding on top. Visqueen protect and...
Stone is getting there and blocks are going up on the second lift. Who can notice the unique touch we have put on one of the stones?
Ceiling joists are in a day ahead of schedule which is great news, more time on the stonework tomorrow. Second lift next week 👍 📍Weston...
Forgot to take photos before we left on Saturday so here is photos before we started this morning. Hoping to get ceiling joists on by...
Before, during and afters of making this small window into what will be double French doors
A bit of stonework is done as you are going to come out the back door of the new extension. Unfortunately, there is a bit of delay in...
The slab has had hardcore and sand put down, wacker bladed and screeded, DPC is down, R400 membrane down, 100mm insulation and then...
Retaining wall is up, sand is down and wacker bladed ready for slab next week, and the first coat of the Visqueen axion guard had been...
Let the tanking commence 👍 📍Weston Rhyn, England
Forgot to take photos at the end of last week so here are the photos before we started yesterday morning. Quite a tricky build this one...
The weekend job is complete. In just 3 weekends we have tiled the floor and completely refitted this amazing new kitchen with loads of...
A bit of a sneak preview of what we have been up to today and yesterday. 2 very long days putting a new kitchen in. Just finishing...
Three wagons full of concrete poured in the footings today. Onto the next stage 👍 📍Weston Rhyn, England
2 layers of steel mesh and over 200 reinforcing L bars for the retaining wall are in. Ready for the concrete pour Friday. 📍Weston Rhyn,...
Plans are on the table and we are ready for an official start on this extension job tomorrow. Nice to be seeing this job start now after...